The main duties are the following :
- Approve the job safety analysis and the method of statement related to the civil and structural activities
- In charge of supervising all civil and building erection works in accordance with site Inspection & test plan
- In charge of replies to Field Changes and Technical Queries
- Ensures the compliance of the works performed with the project drawings
- Ensures the compliance of the works performed with the Client quality standards & specifications
- Knows and uses project drawings and Client specifications in order to perform the Scope of Work
- Shall anticipate the works coming (based on the approved S/C schedule and with the construction manager) studying the project drawings in advance, clarifying with the project engineer the potential questions, verifying that the S/C will be ready to perform its works (critical material available, specialized companies or resources mobilized, Methods of statements issued & approved…)
- Shall ensure that Client free issue items required for its own Scope of Work are delivered in time & make coordination with the Material manager
- Shall ensure that AS BUILT drawings are properly issued and updated by the S/C on a weekly basis- Shall be a safety actor by reporting safety hazardous situation or non conformities
- Shall stop the works when safety or quality issues are found until corrective action is implemented
- Performs all the inspections on site as per ITP (with the support of site QA/QC team when required)
- Updates the own set of project documents (drawings…) with the last revisions issued
- Is the leader of the S/C weekly meeting and issues the Minutes of Meeting
- Follows up the detail schedule with S/C, reports any deviation on weekly basis to the site manager and establishes action plan with S/C to recover the delay
- Opens NCR related to the Scope of Work, propose solution and follows them until they are closed informing the QA/QC manager
- Performs weekly reviews on the compilation of the quality files (by the S/C) & informs QA/QC manager in case of major deviation found- Reviews, comments & supports the QA/QC manager in order to approve the ITP- Updates & signs the ITP with the inspection performed
- Validates on a weekly basis the progress on the Scope of Work through feedbacks to the site manager
- Supports the site manager in order to track the installed quantity on all the Scope of Work
- Track the quantities in order to ensure the remeasurement of the scope of work
- Shall lead tool box with the subcontractor 2 at 3 times by weeks on specific safety or technical points with the support of HSE manager for safety tool box and technical tool box with the site manager
- Issue to the site manager & project engineer a daily report of activities, problems encountered and actions to be taken